Cash incentives for new wind generation systems are available in New York. Incentive levels vary depending on the size of a wind generation system, the tower height, and the class of customer. To be eligible, customers must pay the Systems Benefits Charge/Renewable Portfolio Standard (SBC/RPS) on their utility bill. The incentive level for a farm, municipal and county government, a not-for-profit facility, or a school is higher than the base incentive level; multiplication factors are provided below.

The table below lists base incentive levels for specific wind generation systems, plus an adjustment factor if the tower height varies from the ‘standard tower height’ listed.  For additional information on equipment manufacturers, visit the American Wind Energy Association’s website.

Base Incentive Levels for PON 1098

MANUFACTURER MODEL DESCRIPTION INCENTIVE STANDARD TOWER HEIGHT (ft) TOWER HEIGHT ADJUSTMENT ($/ft difference from standard tower height)
Abundant Renewable Energy ARE110 2.5kW Wind Turbine
$8,750
80
$30
Abundant Renewable Energy ARE442 10kW Wind Turbine
$25,200
100
$60
Aerostar 6 meter 8.6 kW Wind Turbine $23,450 100 $60
Bergey Windpower  BWC XL.1 1 kW Wind Turbine $3,500 80 $30
Bergey Windpower  BWC EXCEL  10 kW Wind Turbine  $23,765 80 $30
Endurance Wind Power S-250 4.25 kW Wind Turbine $14,875 80 $30
Enertech E13 40 kW Wind Turbine $45,500 100 $60
Entegrity Wind Systems EW50 50 kW Wind Turbine $52,500 80 $30
Eoltec Scirocco E5.6-6 6 kW Wind Turbine $19,635 100 $60
Fortis Espada 0.8 kW Wind Turbine $2,100 80 $30
Fortis Montana 5.8 kW Wind Turbine $11,900 80 $30
Fortis Alize 10 kW Wind Turbine $24,500 100 $60
Gaia-Wind 11kW wind turbine 11kW Wind Turbine $40,880 80 $30
MaManna Renewable Energy AOC 15/50 50 kW Wind Turbine $52,500 100 $60
Northern Power Systems North Wind 100 100 kW Wind Turbine 19m rotor $66,500 100 $60
Northern Power Systems North Wind 100 100 kW Wind Turbine 20m rotor $70,000 100 $60
Proven Energy WT2500 2.5 kW Wind Turbine $7,595 80 $30
Proven Energy WT6000 6 kW Wind Turbine $18,480 80 $30
Proven Energy WB6000 15kW Wind Turbine $31,500 100 $60
REDriven, Inc. FD10.0-20K 20 kW Wind Turbine $35,000 100 $60
REDriven, Inc. FD 8.0-10K 10 kW Wind Turbine $22,400 80 $30
REDriven, Inc. FD6.4-5000 5 kW Wind Turbine $20,300 80 $30
REDriven, Inc. FD3.6-2000 2 kW Wind Turbine $8,750 80 $30
Southwest Windpower  Whisper 200  1 kW
Wind Turbine
$3,500 80 $30
Southwest Windpower  Skystream 3.7 1.8 kW (2.4 kW peak) Wind Turbine  $6,300 80 $30
Southwest Windpower  Whisper 500 3 kW 3000 Wind Turbine $8,050 80 $30
Swift Wind
Turbine
Mark II 0.915kW wind Turbine $3,203 80 $30
Wind Energy Solutions WES 5 2.5 kW Wind Turbine $9,100 80 $30
Wind Energy Solutions WES 18 80 kW Wind Turbine $63,000 100 $60
Wind Energy Solutions WES 30 250 kW Wind Turbine $105,000 100 $60
Wind Turbine Industries  Jacobs 31-20 20 kW Wind Turbine $33,069 100 $60

The following table lists multiplication factors for incentives.  If you fall into any of the categories below, multiply the base incentive level derived from the table above by the multiplication factor in the table below to determine your incentive.

Multiplication Factors For Incentives

Residences, Businesses, Institutional, Government

Commercial Farms* and Not-for- Profits**, and Municipalities or Counties

Schools or Colleges that Include Wind in Curriculum***

Customers Participating in the Installation

Multiplier for Second or Third Wind Generator at one Site

1

1.2

1.4

0.75

0.4

* Commercial farms must provide evidence that they have at least $10,000 of farm-related average gross sales, excluding any income from leasing land.

** Not-for-profits must show evidence that they have 501(c)(3) status

*** Schools and colleges that include wind in their curriculum must demonstrate sufficient educational benefits to NYSERDA to qualify for the higher incentive level.

Additionally, the New York Energy $martSM Loan Fund provides interest rate reductions on loans for energy efficiency projects and renewable technologies. Interest rates for loans can be reduced by 4 percent for up to 10 years. Visit http://www.nyserda.org/loanfund/default.asp for more information.

How and When are Cash Incentives Paid

There are a few important facts to know about the incentives offered under this program:

  • Incentive payments are not paid directly to the owner of the wind system

  • Incentives are paid to eligible installers that have been approved to participate in this program

  • The entire incentive must be passed on to the owner of the wind system by the eligible installer

  • Incentives are paid in two installments. Sixty-five percent (65%) of the incentive is paid after the equipment is delivered to the installation site and all required permits, approvals, certificates, etc. from all jurisdictions having authority are secured. The remaining thirty-five percent (35%) is paid when the wind system is grid-connected and approved by your utility. NYSERDA reserves the right to review any installation prior to final incentive payment is made.

Important Note: Because NYSERDA will not process any payments without proof that all permits have been obtained, a customer must work with the installer to obtain all necessary pre-construction permits, approvals, and certificates from all jurisdictions having authority prior to ordering equipment.

Incentives will not be paid for wind systems installed by contractors or individuals that are not on NYSERDA's list of eligible installers. 

Additional benefits of buying a wind system under this program?

All wind systems installed with incentives by this program will come with a full five-year parts and labor warranty. The wind system will include an easy-to-read digital meter allowing customers and installers to monitor system performance. All wind systems will be monitored for energy production, at least twice a year, for two years. If the wind system is not operating at specified performance goals, an installer will inspect the system components. NYSERDA will review each proposed wind system design, all incentive applications, and every customer purchase agreement. The scope of the NYSERDA review shall be limited solely to determining whether NYSERDA's program conditions have been met and shall not include any type of safety review. NYSERDA shall work closely with each eligible installer and monitor their performance throughout the program.

Important Note: NYSERDA is not responsible for assuring that the design, engineering, and construction of the project or installation of any wind system is proper or complies with any particular laws (including patent laws), regulations, codes, or industry standards. NYSERDA does not make any representations of any kind regarding the results to be achieved by the wind systems or the adequacy or safety of such measures.

Required Documents

Customers shall sign the incentive application form and a customer purchase agreement prepared by the installer. The customer purchase agreement will outline total installed costs, provide detailed costs of all major components, identify the expected cash incentive(s), and provide an installation schedule. Customers shall sign off on the packing slip indicating all system components have been delivered to the installation site.
Eligible installers are responsible for all paperwork required under this program.

Choosing an Eligible Installer

The eligible installers list will be updated as new installers are added to the program. Please check the list periodically. The program was launched in June 2003 and new installers continue to be added to the eligible installer list.

Eligible installers have been selected based on their experience installing wind systems, training, education, and recommendations from past customers. Installer performance will be continually monitored through inspections, customer feedback, and ability to meet all program terms and conditions. Installers may be removed from NYSERDA's program if they do not meet the program requirements.

For additional information regarding NYSERDA's New York Energy $martSM Wind Incentive Program and other NYSERDA programs, please call (518) 862-1090, 1-866-NYSERDA, or email info@nyserda.org.

 
Solar
Wind
Biomass Resources
Buying Green Power
Natural Gas
Manufacturing Business Development
Other
School Power Naturally
Funding Opportunities


Success Stories
Useful Links
Library
Photo Gallery

 


Board of Directors | Privacy Policies | Disclaimer | NYSERDA Regulations | Comments?


17 Columbia Circle, Albany, NY 12203-6399    Toll-Free: 1-866-NYSERDA or Local: 518-862-1090    Fax: 518-862-1091
New York City and Buffalo Regional Offices

© 2004 New York State Energy Research and Development Authority
New York State Energy Research and Development Authority
Get Acrobat Reader